156MW Hyperscale DC Expansion
Underground Infrastructure Construction
MMR Group and Turner Construction
$9,900,000.
Lenoir, NC
8 Month Duration
2,600 LF of MV duct banks and 4,500 LF 24-2” telecom duct bank to existing data center under railroad ROW and across undeveloped mountainous terrain. Dynamic schedule and design resulting in 53 change orders totaling $3,300,000.